Delay to Spaces for People measures at Ardmillan Terrace/Henderson Terrace sections

Image credit: City of Edinburgh Council

We received the following notification from the City of Edinburgh Council Spaces for People Team on Thursday 23rd July:

Dear Councillors and Stakeholders,

Further to our email of 17th July (below) and ahead of the implementation of the Gorgie & Dalry Spaces for People measures tomorrow (23 July) we wished to advise you that some elements of the measures will be delayed in arriving on street.

Due to the Scotia Gas Networks (SGN) works on Gorgie Road and Dalry Road at the junction with Ardmillan Terrace we are unable to install some of the proposals in this area until these works are completed. The affected sections of the proposals are on the south side of Gorgie Road from Ardmillan Terrace to Gorgie City Farm and part of the section on the south side of Dalry Road from Henderson Terrace junction to approximately Murieston Crescent.

The completion date for the SGN works is currently scheduled for 31st July 2020, and once the SGN traffic management is removed we will arrange for the remaining measures to be installed.

Kind regards,

Andy

On behalf of the Spaces for People Team


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s